Level 1-5 commissioning. Five levels before handoff.
Commissioning (Cx) verifies that critical facility systems work as designed. Five levels run from L1 factory acceptance to L5 integrated systems testing; the project's commissioning plan governs the detailed sequence.
01 / The 5 levels
What each level covers
- Level 1: Factory Acceptance Test (FAT). Equipment tested at the manufacturer before shipment. UPS, switchgear, generators, chillers, CRAH/CRAC units. Witnessed by the owner's CxA when scope warrants.
- Level 2: Site Acceptance Test (SAT). Pre-functional checks after delivery and install. Visual inspection, settings verification, continuity / megger / insulation tests.
- Level 3: Functional / Start-up. Each system energized and tested standalone. UPS hold-load, generator transfer, cooling reaches setpoint.
- Level 4: Functional Performance Testing. Systems tested against their designed performance criteria following successful start-up.
- Level 5: Integrated Systems Testing. All systems tested together, including failure-mode and load-bank scenarios (utility loss, UPS battery exhaustion, cooling failure) to verify that backup systems engage correctly and the hall maintains operational continuity. The project's commissioning plan governs the detailed sequence.
02 / HexTel's role
Cx support, not the CxA role
HexTel provides structured cabling, rack and stack, and L1-L2 commissioning support in coordination with the owner's commissioning team. We do not act as the third-party Commissioning Authority (that role belongs to the owner-engaged Cx firm). What we provide:
- Witnessed-test attendance and documentation
- Pre-functional check execution and sign-off
- Punch list resolution coordinated with GC + MEP trades
- Final closeout packets: test data, as-builts, training records, owner handoff
- Change-window discipline (MOPs, backout plans) when live load is involved
03 / FAQ
Common questions about Level 1-5 commissioning
- What is Level 1-5 commissioning?
- Level 1-5 commissioning (Cx) is the industry-standard process for verifying that critical facility systems (power, cooling, fire, controls) work as designed before the owner takes operational handoff. Each level adds layered verification, from factory testing of individual components (Level 1) through functional performance testing (Level 4) and integrated systems testing (Level 5). The project's commissioning plan governs the detailed sequence.
- What is Level 1 (L1) commissioning?
- Level 1 is the Factory Acceptance Test (FAT). Equipment is tested at the manufacturer before shipment to confirm it meets spec. Typical components: UPS systems, switchgear, generators, chillers, CRAH/CRAC units. Pass/fail criteria are documented per manufacturer test scripts, with witnessing by the owner's commissioning agent (CxA) when scope warrants.
- What is Level 2 (L2) commissioning?
- Level 2 is the Site Acceptance Test (SAT) and pre-functional checks. Equipment is verified on-site after delivery and installation but before energization: verifying it survived shipping, was installed correctly, and is ready for start-up. Includes visual inspection, settings verification, and continuity / megger / insulation tests.
- What is Level 3 (L3) commissioning?
- Level 3 is Functional / Start-up Testing. Each system is energized and tested standalone: does the UPS hold load, does the generator transfer cleanly, does the cooling system reach setpoint under load. The system is verified to operate within its design parameters in isolation.
- What is Level 4 (L4) commissioning?
- Level 4 is Functional Performance Testing. Systems are tested against their designed performance criteria following successful start-up.
- What is Level 5 (L5) commissioning?
- Level 5 is Integrated Systems Testing. All systems are tested together, including failure-mode and load-bank testing. The data hall is run through realistic failure scenarios (utility loss, UPS battery exhaustion, cooling failure) to verify that backup systems engage correctly and the hall maintains operational continuity. The project's commissioning plan governs the detailed sequence.
- Does HexTel run commissioning, or just support it?
- HexTel provides structured cabling, rack and stack, and L1-L2 commissioning support in coordination with the owner's commissioning team. We are not the third-party CxA on a project (that role belongs to the owner-engaged commissioning firm).
Next step
Need install + Cx support on a data center build?
A 30-minute scoping call covers your Cx authority, MEP scope, change-window posture, and the cleanest path to acceptance.
